August 03, 2018 Letting 10:00 AM
015-62G15

Bulletin Description

Clean and paint the existing truss on the structure carrying IL 7 over the Cal-Sag Channel in the villages of Palos Heights and Palos Hills.
Region District DBE % VBP % Federal Project #
1 1 9.00 0.00 STPMW7B(995)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Cook
  • FAU 3578
  • 2018-009-BP
  • C-91-182-18
  • 0-01289-1000
Contract Specifics
Pursuant to the Rules for Prequalification of Contractors and Issuance of Plans and Proposals, 44 Illinois Administrative Code 650.70,... "This contract requires, in addition to the normal IDOT prequalifications requirements, that the Contractor be SSPC - QP1 and QP2 certified. Evidence of certification must be provided prior to receiving authorization to bid." Contractors are required to submit copies of current certificates for each Letting. These certificates must be submitted along with the contractor's original BC 57 Affidavit of Availability. (BC 57)
60 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (3 Submitted / 2 Answered ) Questions not accepted as of July 24, 2018 04:30 PM.

  • Would we be able to erect a suspended platform underneath the structure and under the truss (maintaining proper clearance) over the road?
    Platforms are allowed but Contractor will be required to obtain Coast Guard approval for any work that may interfere with navigational operations of navigable waters, ensure proper clearance over roadway and provide calculations that assure the structural integrity of the bridge when it supports the platform. Calculations and drawings shall be signed and sealed by a structural engineer licensed in the state of Illinois. (07/25/2018)

  • Being that this project is being advertised towards the end of the summer with the fall season approaching would it be possible to begin this project in the spring without being charged working days? It will take 30-60 days for contract award and execution. The weather is also something to take into consideration with the fall having significant rain.
    The District has no objections to have this contract start in the spring of next year. No working days will be charged to the contract. (07/24/2018)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
63301235 FOOT REMOVE AND REERECT STEEL PLATE BEAM GUARDRAIL, ATTACHED TO STRUCTURES Base items 500.000
64300450 EACH IMPACT ATTENUATORS (NON-REDIRECTIVE), TEST LEVEL 3 Base items 2.000
67000400 CAL MO ENGINEER'S FIELD OFFICE, TYPE A Base items 9.000
67100100 L SUM MOBILIZATION Base items 1.000
70300904 FOOT PAVEMENT MARKING TAPE, TYPE IV 4" Base items 8,894.000
70400100 FOOT TEMPORARY CONCRETE BARRIER Base items 675.000
70400200 FOOT RELOCATE TEMPORARY CONCRETE BARRIER Base items 675.000
70600350 EACH IMPACT ATTENUATORS, RELOCATE (NON- REDIRECTIVE), TEST LEVEL 3 Base items 2.000
78000200 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 4" Base items 1,757.000
78000600 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 12" Base items 17.000
78008210 FOOT POLYUREA PAVEMENT MARKING TYPE I - LINE 4" Base items 202.000
78100100 EACH RAISED REFLECTIVE PAVEMENT MARKER Base items 46.000
78200011 EACH BARRIER WALL REFLECTORS, TYPE C Base items 32.000
78300200 EACH RAISED REFLECTIVE PAVEMENT MARKER REMOVAL Base items 46.000
X0327980 SQ FT PAVEMENT MARKING REMOVAL - WATER BLASTING Base items 603.000
X7010216 L SUM TRAFFIC CONTROL AND PROTECTION, (SPECIAL) Base items 1.000
X7015005 CAL DA CHANGEABLE MESSAGE SIGN Base items 30.000
X7030005 SQ FT TEMPORARY PAVEMENT MARKING REMOVAL Base items 2,965.000
Z0007112 L SUM CONTAINMENT AND DISPOSAL OF LEAD PAINT CLEANING RESIDUES Base items 1.000
Z0010501 L SUM CLEANING AND PAINTING STEEL BRIDGE NO. 1 Base items 1.000
Z0030850 SQ FT TEMPORARY INFORMATION SIGNING Base items 51.400
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.