March 05, 2021 Letting 12:00 PM
4LR-M2004

Bulletin Description

The Buckheart Mine Highwall Remedial Project is for the repair of an eroded sideslope and drainageways at the Buckheart Mine abandoned mine site by the Illinois Department of Natural Resources using federal abandoned mined lands funds. 
Region District DBE % VBP %
0 0 20.00 0.00
County(s) Project # Name
Fulton AML-GFuE-2004 Buckheart Mine Highwall Remedial Project
Contract Specifics
A voluntary pre-bid meeting will be held on Tuesday, February 16, 2021 at 11:00 AM in the Project Site at east of the intersection of Illinois Route 78 and County Highway 30 (Old Weaver Road), approximately five and one-half miles south of Canton, IL. Location Notes - Section 35 of Township 6 North – Range 4 East, in Fulton County. Click here for map
Project Labor Agreement

The Contract shall end on or before 06/30/2022 with an interim progress date (when all earthwork, erosion control, permanent and temporary seeding, and mulching must be completed by) of 09/01/2021.

No More Contract Specifics

Ask Subscribe Questions and Answers (1 Submitted / 1 Answered ) Questions not accepted as of February 23, 2021 04:30 PM.

  • The plan set does not appear to show the existing grades in the areas of work. Can you please provide a plan set that shows the existing grades so we can compare to proposed grades?
    A plan set showing existing grades is not available for grade comparison. We have estimated that 3,555 cubic yards of earthen material is needed for a 1' average thickness over the eroded sideslope area and 547 cubic yards of earthen material is needed for a 1' average thickness over the eroded ditch areas for a total of 4,102 cubic yards. This material will be obtained from the borrow area. Placement and grading is considered incidental to earth excavation. Surveys of the borrow area will be conducted before and after excavation to determine the payment quantity. (02/23/2021)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
25100115 ACRE MULCH, METHOD 2 Base items 1.700
25100900 SQ YD TURF REINFORCEMENT MAT Base items 1,642.000
28100725 SQ YD STONE DUMPED RIPRAP, CLASS B3 Base items 318.000
40200800 TON AGGREGATE SURFACE COURSE, TYPE B Base items 97.000
NRM20110 L SUM SPECIAL CLEARING Base items 1.000
NRM20210 CU YD EARTH EXCAVATION Base items 4,102.000
NRM25040 POUND NITROGEN FERTILIZER NUTRIENT Base items 1,080.000
NRM25050 POUND PHOSPHORUS FERTILIZER NUTRIENT Base items 1,270.000
NRM25060 POUND POTASSIUM FERTILIZER NUTRIETNT Base items 3,150.000
NRM25070 TON AGRICULTURAL GROUND LIMESTONE Base items 5.600
NRM25090 ACRE SEEDING Base items 4.500
NRM28031 FOOT TEMPORARY DITCH CHECK Base items 20.000
NRM28610 SQ YD SPECIAL EXCELSIOR BLANKET Base items 10,664.000
NRM67110 L SUM MOBILIZATION Base items 1.000
No More Pay Items