**QA Environment**
Home > Notice of Letting > Contract Detail

March 08, 2019 Letting 10:00 AM
038-78618

Bulletin Description

Removal and replacement of double barrel 7'x 7' box culvert SN 073-7074 on IL 13 in Perry.
Region District DBE % VBP % Federal Project #
5 9 0.00 0.00 STP9WU7(001)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Perry
  • FAP 103
  • 102B-2
  • C-99-011-18
  • 9-00489-0000
Contract Specifics
25 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 2 Answered ) Questions not accepted as of February 26, 2019 04:30 PM.

  • The drawings indicate that the last two box culverts will need to be tied together (note on sheet 13) as per the last drawing (sheet 17). The detail on sheet 17 details for a single run. This project is a double run. In order to tie the culverts together, the joint spacing will need to be staggered, Is this acceptable? Also, the spacing between the two parallel culverts are noted to be 3" (Sheet 12), the restrain angle is 4", therefore the gap will need to be greater than 4".
    An addendum is forthcoming to clarify this issue. The culvert ties shown on sheet 17 of the plans will only be required on the exterior walls of the culvert. The 3" space between the culverts will be filled with Class SI concrete. With no culvert ties between the two box culverts, the joint spacing will not have to be staggered and the 3" spacing will not have to be increased. (02/27/2019)

  • Is a protection board required for the waterproofing membrane?-or drainage mat?
    An addendum is forthcoming on this project. The special provision Membrane Waterproofing for Buried Structures will be revised and include the requirements for this work. (02/19/2019)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
20200100 CU YD EARTH EXCAVATION Base items 302.000
20300100 CU YD CHANNEL EXCAVATION Base items 50.000
20400800 CU YD FURNISHED EXCAVATION Base items 15.000
20700220 CU YD POROUS GRANULAR EMBANKMENT Base items 374.000
25000200 ACRE SEEDING, CLASS 2 Base items 0.100
25000400 POUND NITROGEN FERTILIZER NUTRIENT Base items 9.000
25000500 POUND PHOSPHORUS FERTILIZER NUTRIENT Base items 9.000
25000600 POUND POTASSIUM FERTILIZER NUTRIENT Base items 9.000
25000700 TON AGRICULTURAL GROUND LIMESTONE Base items 0.200
25100630 SQ YD EROSION CONTROL BLANKET Base items 484.000
28000250 POUND TEMPORARY EROSION CONTROL SEEDING Base items 50.000
28000400 FOOT PERIMETER EROSION BARRIER Base items 135.000
42000060 SQ YD WELDED WIRE REINFORCEMENT Base items 156.000
44201347 SQ YD CLASS C PATCHES, TYPE IV, 9 INCH Base items 156.000
48300300 SQ YD PORTLAND CEMENT CONCRETE SHOULDERS 8" Base items 48.000
50100100 EACH REMOVAL OF EXISTING STRUCTURES Base items 1.000
50800205 POUND REINFORCEMENT BARS, EPOXY COATED Base items 2,320.000
54003000 CU YD CONCRETE BOX CULVERTS Base items 26.200
54010707 FOOT PRECAST CONCRETE BOX CULVERTS 7' X 7' Base items 120.000
67100100 L SUM MOBILIZATION Base items 1.000
70100450 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 Base items 1.000
70101830 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD BLR 21 Base items 1.000
70103815 CAL DA TRAFFIC CONTROL SURVEILLANCE Base items 8.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 46.000
70300100 FOOT SHORT TERM PAVEMENT MARKING Base items 8.000
70300150 SQ FT SHORT TERM PAVEMENT MARKING REMOVAL Base items 3.000
70300220 FOOT TEMPORARY PAVEMENT MARKING - LINE 4" Base items 128.000
78001110 FOOT PAINT PAVEMENT MARKING - LINE 4" Base items 128.000
X0900064 SQ YD MEMBRANE WATERPROOFING SYSTEM FOR BURIED STRUCTURES Base items 127.000
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.