March 08, 2019 Letting 10:00 AM
02A-MV063

Bulletin Description

Rehabilitate Taxiway A1
Region District DBE % VBP % Federal Project #
5 9 10.00 0.00 317SBGPTBD
County(s) IL Project # Airport Sponsor City
  • Jefferson
MVN 4684 Mt. Vernon Mt. Vernon Airport Authority Mt. Vernon
Contract Specifics
The time limit to award this item has been changed from 45 days to 60 days after the scheduled letting.
15 Calendar Days
No More Contract Specifics

Ask Subscribe Questions and Answers (0 Submitted / 0 Answered ) Questions not accepted as of February 26, 2019 04:30 PM.

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
AR150510 L SUM ENGINEER'S FIELD OFFICE Base items 1.000
AR150520 L SUM MOBILIZATION Base items 1.000
AR401613 TON BIT. SURF. CSE.-METHOD I, SUPERPAVE Base items 475.000
AR401650 SQ YD BITUMINOUS PAVEMENT MILLING Base items 1,970.000
AR603510 GALLON BITUMINOUS TACK COAT Base items 500.000
AR620520 SQ FT PAVEMENT MARKING-WATERBORNE Base items 1,930.000
AR620525 SQ FT PAVEMENT MARKING-BLACK BORDER Base items 1,375.000
AR620900 SQ FT PAVEMENT MARKING REMOVAL Base items 430.000
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.