June 14, 2019 Letting 10:00 AM
132-91755

Bulletin Description

Contruction of a bikeway along Old US 66, 1.1 miles South of E 850 North Road to E 550 North Road.
Region District DBE % VBP % Federal Project #
3 5 4.00 0.00 RZFE(083)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • McLean
  • FAS 1488
  • 17-00001-05-BT
  • C-95-096-18
  • 0-01729-5007
Contract Specifics
90 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (4 Submitted / 3 Answered ) Questions not accepted as of June 04, 2019 04:30 PM.

  • In response to answer of question #1. There are OH utility lines on the east side of Rt. 66 at the main & the spur bridge locations. Are OH power lines as well as Frontier lines present here? We have concerns with installing the bridges with these lines in place. Can these lines be moved below grade or to ground level & protected in order to facilitate the installation of the pedestrian bridge work? Thank you.
    From our information the overhead lines at the mainline pedestrian bridge are telephone. The overhead lines at the spur bridge are electric. Neither conflicts with construction of the project. The Contractor would need to make arrangements with the utility if the lines conflict with his operations. (06/04/2019)

  • There are OH utility lines marked "T" on the plan and profile sheets at the pedestrian bridge locations. It is assumed at this time these are OH telephone lines. Special provisions page 7 states that Frontier Telephone Lines are to be relocated throughout project. Is there a plan to relocate, lower, or otherwise adjust the OH utility lines specifically at the pedestrian bridge locations? Are there other lines besides just Frontier telephone at these locations?
    Frontier has a coper cable and fiber optic line from the south end of the project to CH 36. The fiber optic line continues along the east side of the project to the north end. The coper cable is overhead at the mainline pedestrian bridge. Frontier may need to make utility adjustments at several locations. Generally, arrangements for adjusting utilities would be made by the County prior to construction. (05/30/2019)

  • I was looking to verify a few items on the bridge. Is the bridge to have vertical pickets? Is the rub rail steel or wood? Is there a completion date for the project? Thank you!
    Both the pickets and rubrails for the proposed bridge should be the most economical and practical options covered by the special provision. In short, simply comply with the special provision. No completion date was included other than that dictated by the working days allowed. See BDE Special Provision Working Days on page 98. (05/30/2019)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
20200100 CU YD EARTH EXCAVATION Base items 3,865.000
20400800 CU YD FURNISHED EXCAVATION Base items 3,080.000
20800150 CU YD TRENCH BACKFILL Base items 16.000
21101615 SQ YD TOPSOIL FURNISH AND PLACE, 4" Base items 35,598.000
25000200 ACRE SEEDING, CLASS 2 Base items 7.500
25000400 POUND NITROGEN FERTILIZER NUTRIENT Base items 663.000
25000500 POUND PHOSPHORUS FERTILIZER NUTRIENT Base items 663.000
25000600 POUND POTASSIUM FERTILIZER NUTRIENT Base items 663.000
25100115 ACRE MULCH, METHOD 2 Base items 7.500
28000250 POUND TEMPORARY EROSION CONTROL SEEDING Base items 737.000
28000305 FOOT TEMPORARY DITCH CHECKS Base items 40.000
28000400 FOOT PERIMETER EROSION BARRIER Base items 25,837.000
28000500 EACH INLET AND PIPE PROTECTION Base items 8.000
28100107 SQ YD STONE RIPRAP, CLASS A4 Base items 99.000
35100100 TON AGGREGATE BASE COURSE, TYPE A Base items 10,869.000
40200100 TON AGGREGATE SURFACE COURSE, TYPE A Base items 452.000
40300200 TON BITUMINOUS MATERIALS (PRIME COAT) Base items 5.400
40300400 TON BITUMINOUS MATERIALS (COVER AND SEAL COATS) Base items 11.700
40300500 TON COVER COAT AGGREGATE Base items 52.000
40300600 TON SEAL COAT AGGREGATE Base items 41.000
40600275 POUND BITUMINOUS MATERIALS (PRIME COAT) Base items 47,373.000
40600290 POUND BITUMINOUS MATERIALS (TACK COAT) Base items 4,604.000
40600627 TON LEVELING BINDER (MACHINE METHOD), IL-9.5FG, N50 Base items 1,760.000
40603310 TON HOT-MIX ASPHALT SURFACE COURSE, MIX "C", N50 Base items 1,723.000
42400300 SQ FT PORTLAND CEMENT CONCRETE SIDEWALK 6 INCH Base items 567.000
42400800 SQ FT DETECTABLE WARNINGS Base items 183.000
44000100 SQ YD PAVEMENT REMOVAL Base items 304.000
48101200 TON AGGREGATE SHOULDERS, TYPE B Base items 1,308.000
50104400 EACH CONCRETE HEADWALL REMOVAL Base items 1.000
50200100 CU YD STRUCTURE EXCAVATION Base items 5.000
50300225 CU YD CONCRETE STRUCTURES Base items 47.200
50300300 SQ YD PROTECTIVE COAT Base items 70.000
50301350 CU YD CONCRETE SUPERSTRUCTURE (APPROACH SLAB) Base items 23.600
50800105 POUND REINFORCEMENT BARS Base items 3,730.000
50800205 POUND REINFORCEMENT BARS, EPOXY COATED Base items 8,280.000
51200957 FOOT FURNISHING METAL SHELL PILES 12" X 0.250" Base items 200.000
51202305 FOOT DRIVING PILES Base items 200.000
51203200 EACH TEST PILE METAL SHELLS Base items 4.000
52100520 EACH ANCHOR BOLTS, 1" Base items 16.000
54001001 EACH BOX CULVERT END SECTIONS, CULVERT NO. 1 Base items 1.000
54001002 EACH BOX CULVERT END SECTIONS, CULVERT NO. 2 Base items 1.000
54002020 EACH EXPANSION BOLTS 3/4 INCH Base items 61.000
54003000 CU YD CONCRETE BOX CULVERTS Base items 13.800
54010403 FOOT PRECAST CONCRETE BOX CULVERTS 4' X 3' Base items 12.000
54213660 EACH PRECAST REINFORCED CONCRETE FLARED END SECTIONS 15" Base items 1.000
54248510 CU YD CONCRETE COLLAR Base items 0.600
54261718 EACH STEEL FLARED END SECTIONS 18" Base items 6.000
54261818 EACH STEEL FLARED END SECTIONS, EQUIVALENT ROUND-SIZE 18" Base items 8.000
542D0223 FOOT PIPE CULVERTS, CLASS D, TYPE 1 18" Base items 102.000
542D5473 FOOT PIPE CULVERTS, CLASS D, TYPE 1 EQUIVALENT ROUND-SIZE 18" Base items 488.000
58600101 CU YD GRANULAR BACKFILL FOR STRUCTURES Base items 64.000
58700300 SQ FT CONCRETE SEALER Base items 972.000
67100100 L SUM MOBILIZATION Base items 1.000
72000100 SQ FT SIGN PANEL - TYPE 1 Base items 173.000
72800100 FOOT TELESCOPING STEEL SIGN SUPPORT Base items 564.000
78000100 SQ FT THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 151.000
78000200 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 4" Base items 990.000
78000600 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 12" Base items 260.000
78000650 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 24" Base items 40.000
X0300010 POUND BITUMINOUS MATERIALS (FOG SEAL) Base items 4,856.000
X0322508 SQ FT PEDESTRIAN TRUSS SUPERSTRUCTURE Base items 3,850.000
X0323991 FOOT SURFACE MOUNT LANE SEPARATOR Base items 69.000
X0350805 EACH FOLD DOWN BOLLARDS Base items 16.000
X6640535 FOOT CHAIN LINK FENCE, 6' ATTACHED TO STRUCTURE Base items 20.000
X6640560 FOOT CHAIN LINK FENCE, 6' (SPECIAL) Base items 20.000
X7010216 L SUM TRAFFIC CONTROL AND PROTECTION, (SPECIAL) Base items 1.000
XX008340 FOOT TIMBER BRIDGE APPROACH RAILING Base items 160.000
Z0013798 L SUM CONSTRUCTION LAYOUT Base items 1.000
Z0076600 HOUR TRAINEES Base items 1,000.000 $0.80
Z0076604 HOUR TRAINEES TRAINING PROGRAM GRADUATE Base items 1,000.000 $15.00
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.