20200100
|
CU YD
|
EARTH EXCAVATION
|
Base items
|
2,301.000
|
|
20400800
|
CU YD
|
FURNISHED EXCAVATION
|
Base items
|
107.000
|
|
20700220
|
CU YD
|
POROUS GRANULAR EMBANKMENT
|
Base items
|
153.000
|
|
21001000
|
SQ YD
|
GEOTECHNICAL FABRIC FOR GROUND STABILIZATION
|
Base items
|
161.000
|
|
25000300
|
ACRE
|
SEEDING, CLASS 3
|
Base items
|
0.760
|
|
25000400
|
POUND
|
NITROGEN FERTILIZER NUTRIENT
|
Base items
|
69.000
|
|
25000500
|
POUND
|
PHOSPHORUS FERTILIZER NUTRIENT
|
Base items
|
69.000
|
|
25000600
|
POUND
|
POTASSIUM FERTILIZER NUTRIENT
|
Base items
|
69.000
|
|
25100115
|
ACRE
|
MULCH, METHOD 2
|
Base items
|
0.760
|
|
28000305
|
FOOT
|
TEMPORARY DITCH CHECKS
|
Base items
|
232.000
|
|
28000400
|
FOOT
|
PERIMETER EROSION BARRIER
|
Base items
|
1,843.000
|
|
28100125
|
SQ YD
|
STONE RIPRAP, CLASS B3
|
Base items
|
173.000
|
|
28100207
|
TON
|
STONE RIPRAP, CLASS A4
|
Base items
|
58.000
|
|
28200200
|
SQ YD
|
FILTER FABRIC
|
Base items
|
89.000
|
|
35101800
|
SQ YD
|
AGGREGATE BASE COURSE, TYPE B 6"
|
Base items
|
3,411.000
|
|
40600275
|
POUND
|
BITUMINOUS MATERIALS (PRIME COAT)
|
Base items
|
8,335.000
|
|
40600295
|
POUND
|
POLYMERIZED BITUMINOUS MATERIALS (TACK COAT)
|
Base items
|
76,803.000
|
|
40600627
|
TON
|
LEVELING BINDER (MACHINE METHOD), IL-9.5FG, N50
|
Base items
|
4,873.000
|
|
40600982
|
SQ YD
|
HOT-MIX ASPHALT SURFACE REMOVAL - BUTT JOINT
|
Base items
|
98.000
|
|
40603310
|
TON
|
HOT-MIX ASPHALT SURFACE COURSE, MIX "C", N50
|
Base items
|
4,420.000
|
|
40800050
|
TON
|
INCIDENTAL HOT-MIX ASPHALT SURFACING
|
Base items
|
91.000
|
|
48101500
|
SQ YD
|
AGGREGATE SHOULDERS, TYPE B 6"
|
Base items
|
939.000
|
|
48102100
|
TON
|
AGGREGATE WEDGE SHOULDER, TYPE B
|
Base items
|
2,173.000
|
|
48203009
|
SQ YD
|
HOT-MIX ASPHALT SHOULDERS, 3"
|
Base items
|
3,032.000
|
|
50102400
|
CU YD
|
CONCRETE REMOVAL
|
Base items
|
11.700
|
|
50200100
|
CU YD
|
STRUCTURE EXCAVATION
|
Base items
|
239.000
|
|
50300225
|
CU YD
|
CONCRETE STRUCTURES
|
Base items
|
7.300
|
|
50800105
|
POUND
|
REINFORCEMENT BARS
|
Base items
|
872.000
|
|
54002020
|
EACH
|
EXPANSION BOLTS 3/4 INCH
|
Base items
|
36.000
|
|
54010403
|
FOOT
|
PRECAST CONCRETE BOX CULVERTS 4' X 3'
|
Base items
|
60.000
|
|
54010404
|
FOOT
|
PRECAST CONCRETE BOX CULVERTS 4' X 4'
|
Base items
|
18.000
|
|
54010606
|
FOOT
|
PRECAST CONCRETE BOX CULVERTS 6' X 6'
|
Base items
|
26.000
|
|
54205059
|
FOOT
|
PIPE CULVERTS, SPECIAL 24"
|
Base items
|
58.000
|
|
54260315
|
FOOT
|
TRAVERSABLE PIPE GRATE FOR CONCRETE END SECTION
|
Base items
|
10.500
|
|
60100935
|
FOOT
|
PIPE DRAINS 10"
|
Base items
|
20.000
|
|
60218300
|
EACH
|
MANHOLES, TYPE A, 4'-DIAMETER, TYPE 1 FRAME, OPEN LID
|
Base items
|
1.000
|
|
60238800
|
EACH
|
INLETS, TYPE A
|
Base items
|
1.000
|
|
63000001
|
FOOT
|
STEEL PLATE BEAM GUARDRAIL, TYPE A, 6 FOOT POSTS
|
Base items
|
1,000.000
|
|
63100167
|
EACH
|
TRAFFIC BARRIER TERMINAL, TYPE 1 (SPECIAL) TANGENT
|
Base items
|
8.000
|
|
63200310
|
FOOT
|
GUARDRAIL REMOVAL
|
Base items
|
1,917.000
|
|
67100100
|
L SUM
|
MOBILIZATION
|
Base items
|
1.000
|
|
70300220
|
FOOT
|
TEMPORARY PAVEMENT MARKING - LINE 4"
|
Base items
|
2,120.000
|
|
78001110
|
FOOT
|
PAINT PAVEMENT MARKING - LINE 4"
|
Base items
|
61,600.000
|
|
X2010400
|
UNIT
|
STUMP REMOVAL ONLY
|
Base items
|
332.000
|
|
X7010216
|
L SUM
|
TRAFFIC CONTROL AND PROTECTION, (SPECIAL)
|
Base items
|
1.000
|
|
Z0012755
|
SQ FT
|
STRUCTURAL REPAIR OF CONCRETE (DEPTH GREATER THAN 5 INCHES)
|
Base items
|
12.000
|
|
Z0013798
|
L SUM
|
CONSTRUCTION LAYOUT
|
Base items
|
1.000
|
|
Z0026408
|
SQ FT
|
TEMPORARY SHEET PILING (SPECIAL)
|
Base items
|
988.000
|
|
Z0034105
|
TON
|
MATERIAL TRANSFER DEVICE
|
Base items
|
9,224.000
|
|
Z0054500
|
TON
|
ROCK FILL
|
Base items
|
158.000
|
|