Bulletin Description

(3.1 mile) Standard overlay and ADA improvements on Narragansett Ave., from Cortland St. to Nagle Ave. in the City of Chicago, Jefferson Township.
Region District DBE % VBP % Federal Project #
1 1 17.00 0.00 STP7BP4(798)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Cook
  • FAU 2783
  • 2019-073-RS&SW
  • C-91-438-19
  • 1-80431-0000
Contract Specifics
70 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (0 Submitted / 0 Answered ) Questions not accepted as of July 21, 2020 04:30 PM.

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
20200100 CU YD EARTH EXCAVATION Base items 45.000
21101615 SQ YD TOPSOIL FURNISH AND PLACE, 4" Base items 800.000
25200110 SQ YD SODDING, SALT TOLERANT Base items 800.000
25200200 UNIT SUPPLEMENTAL WATERING Base items 8.000
40200300 SQ YD AGGREGATE SURFACE COURSE, TYPE A 4" Base items 130.000
40600290 POUND BITUMINOUS MATERIALS (TACK COAT) Base items 34,479.000
40600400 TON MIXTURE FOR CRACKS, JOINTS, AND FLANGEWAYS Base items 76.000
40600982 SQ YD HOT-MIX ASPHALT SURFACE REMOVAL - BUTT JOINT Base items 725.000
40603200 TON POLYMERIZED HOT-MIX ASPHALT BINDER COURSE, IL-4.75, N50 Base items 2,770.000
40604062 TON HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "D", N70 Base items 4,230.000
42001300 SQ YD PROTECTIVE COAT Base items 3,416.000
42300200 SQ YD PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, 6 INCH Base items 70.000
42300400 SQ YD PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, 8 INCH Base items 309.000
42400200 SQ FT PORTLAND CEMENT CONCRETE SIDEWALK 5 INCH Base items 2,122.000
42400410 SQ FT PORTLAND CEMENT CONCRETE SIDEWALK 8 INCH Base items 876.000
44000159 SQ YD HOT-MIX ASPHALT SURFACE REMOVAL, 2 1/2" Base items 50,354.000
44000200 SQ YD DRIVEWAY PAVEMENT REMOVAL Base items 379.000
44000600 SQ FT SIDEWALK REMOVAL Base items 3,029.000
44201761 SQ YD CLASS D PATCHES, TYPE I, 10 INCH Base items 25.000
44201765 SQ YD CLASS D PATCHES, TYPE II, 10 INCH Base items 575.000
44201769 SQ YD CLASS D PATCHES, TYPE III, 10 INCH Base items 400.000
44201771 SQ YD CLASS D PATCHES, TYPE IV, 10 INCH Base items 4,000.000
60252800 EACH CATCH BASINS TO BE RECONSTRUCTED Base items 3.000
60255500 EACH MANHOLES TO BE ADJUSTED Base items 6.000
60257900 EACH MANHOLES TO BE RECONSTRUCTED Base items 9.000
60262700 EACH INLETS TO BE RECONSTRUCTED Base items 7.000
60266600 EACH VALVE BOXES TO BE ADJUSTED Base items 1.000
60300105 EACH FRAMES AND GRATES TO BE ADJUSTED Base items 62.000
60300305 EACH FRAMES AND LIDS TO BE ADJUSTED Base items 2.000
60406520 EACH FRAMES AND LIDS, OPEN LID (CITY OF CHICAGO) Base items 82.000
60406530 EACH FRAMES AND LIDS, CLOSED LID (CITY OF CHICAGO) Base items 14.000
66900200 CU YD NON-SPECIAL WASTE DISPOSAL Base items 45.000
66900530 EACH SOIL DISPOSAL ANALYSIS Base items 5.000
66901001 L SUM REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN Base items 1.000
66901003 L SUM REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT Base items 1.000
66901006 CAL DA REGULATED SUBSTANCES MONITORING Base items 12.000
67000400 CAL MO ENGINEER'S FIELD OFFICE, TYPE A Base items 9.000
67100100 L SUM MOBILIZATION Base items 1.000
70102620 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701501 Base items 1.000
70102640 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701801 Base items 1.000
70300100 FOOT SHORT TERM PAVEMENT MARKING Base items 17,616.000
70300150 SQ FT SHORT TERM PAVEMENT MARKING REMOVAL Base items 5,872.000
70300210 SQ FT TEMPORARY PAVEMENT MARKING LETTERS AND SYMBOLS Base items 2,405.000
70300220 FOOT TEMPORARY PAVEMENT MARKING - LINE 4" Base items 33,848.000
70300240 FOOT TEMPORARY PAVEMENT MARKING - LINE 6" Base items 9,039.000
70300250 FOOT TEMPORARY PAVEMENT MARKING - LINE 8" Base items 14,922.000
70300260 FOOT TEMPORARY PAVEMENT MARKING - LINE 12" Base items 225.000
70300280 FOOT TEMPORARY PAVEMENT MARKING - LINE 24" Base items 3,229.000
70300520 FOOT PAVEMENT MARKING TAPE, TYPE III 4" Base items 4,404.000
78000100 SQ FT THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 1,152.000
78000200 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 4" Base items 33,848.000
78000400 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 6" Base items 9,039.000
78000500 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 8" Base items 14,922.000
78000600 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 12" Base items 225.000
78000650 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 24" Base items 6,073.000
78009000 SQ FT MODIFIED URETHANE PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 78.000
78009004 FOOT MODIFIED URETHANE PAVEMENT MARKING - LINE 4" Base items 75.000
78100100 EACH RAISED REFLECTIVE PAVEMENT MARKER Base items 40.000
78300200 EACH RAISED REFLECTIVE PAVEMENT MARKER REMOVAL Base items 40.000
85000200 EACH MAINTENANCE OF EXISTING TRAFFIC SIGNAL INSTALLATION Base items 1.000
87301215 FOOT ELECTRIC CABLE IN CONDUIT, SIGNAL NO. 14 2C Base items 50.000
88600600 FOOT DETECTOR LOOP REPLACEMENT Base items 400.000
89500400 EACH RELOCATE EXISTING PEDESTRIAN PUSH-BUTTON Base items 2.000
89502300 FOOT REMOVE ELECTRIC CABLE FROM CONDUIT Base items 40.000
89502376 EACH REBUILD EXISTING HANDHOLE Base items 1.000
X0320050 L SUM CONSTRUCTION LAYOUT (SPECIAL) Base items 1.000
X4240800 SQ FT DETECTABLE WARNINGS (SPECIAL) Base items 398.000
X5537800 FOOT STORM SEWERS TO BE CLEANED 12" Base items 1,080.000
X7030005 SQ FT TEMPORARY PAVEMENT MARKING REMOVAL Base items 31,612.000
X7800800 SQ FT HOT SPRAY THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 1,253.000
Z0004562 FOOT COMBINATION CONCRETE CURB AND GUTTER REMOVAL AND REPLACEMENT Base items 8,114.000
Z0018500 EACH DRAINAGE STRUCTURES TO BE CLEANED Base items 144.000
Z0030850 SQ FT TEMPORARY INFORMATION SIGNING Base items 51.400
Z0033700 FOOT LONGITUDINAL JOINT SEALANT Base items 17,600.000
Z0076600 HOUR TRAINEES Base items 500.000 $0.80
Z0076604 HOUR TRAINEES TRAINING PROGRAM GRADUATE Base items 500.000 $15.00