(1,444-Ft.) SMART Overlay and ADA Ramp Improvement. Location: IL 64 (North Ave.) Sheffield Ave to Halsted St. in The City of Chicago in Cook County.
Region District DBE % VBP % Federal Project #
1 1 0.00 0.00
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Cook
  • FAP 307
  • 2020-096-RS
  • C-91-293-20
  • 1-80584-0000
Contract Specifics
25 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (1 Submitted / 1 Answered ) Questions not accepted as of January 05, 2021 04:30 PM.

  • Is there a PROJECT SPECIFIC - REMOVAL AND DISPOSAL OF REGULATED SUBSTANCE DOCUMENT for this contract?
    The posted Special Provisions contain a PROJECT SPECIFIC - REMOVAL AND DISPOSAL OF REGULATED SUBSTANCE provision on pages 29 & 30. It did not show up in the Table of Contents, but it is included in the document. The project should be bid according to the Standard Specifications for Road and Bridge Construction, Highway Standards, and the plans and specifications published online. (12/21/2020)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
20200100 CU YD EARTH EXCAVATION Base items 8.000
40600290 POUND BITUMINOUS MATERIALS (TACK COAT) Base items 4,188.000
40600400 TON MIXTURE FOR CRACKS, JOINTS, AND FLANGEWAYS Base items 1.000
40600982 SQ YD HOT-MIX ASPHALT SURFACE REMOVAL - BUTT JOINT Base items 220.000
40601005 TON HOT-MIX ASPHALT REPLACEMENT OVER PATCHES Base items 37.000
40604172 TON POLYMERIZED HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "E", N70 Base items 912.000
42300400 SQ YD PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT, 8 INCH Base items 45.000
42400200 SQ FT PORTLAND CEMENT CONCRETE SIDEWALK 5 INCH Base items 578.000
44000156 SQ YD HOT-MIX ASPHALT SURFACE REMOVAL, 1 3/4" Base items 9,306.000
44000200 SQ YD DRIVEWAY PAVEMENT REMOVAL Base items 45.000
44000600 SQ FT SIDEWALK REMOVAL Base items 600.000
44002216 SQ YD HOT-MIX ASPHALT REMOVAL OVER PATCHES, 4" Base items 161.000
44201765 SQ YD CLASS D PATCHES, TYPE II, 10 INCH Base items 25.000
44201769 SQ YD CLASS D PATCHES, TYPE III, 10 INCH Base items 85.000
44201771 SQ YD CLASS D PATCHES, TYPE IV, 10 INCH Base items 30.000
60237460 EACH INLETS, TYPE A, TYPE 23 FRAME AND GRATE Base items 1.000
60255700 EACH MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, OPEN LID Base items 3.000
60255800 EACH MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, CLOSED LID Base items 3.000
66900200 CU YD NON-SPECIAL WASTE DISPOSAL Base items 8.000
66900530 EACH SOIL DISPOSAL ANALYSIS Base items 2.000
66901001 L SUM REGULATED SUBSTANCES PRE-CONSTRUCTION PLAN Base items 1.000
66901003 L SUM REGULATED SUBSTANCES FINAL CONSTRUCTION REPORT Base items 1.000
66901006 CAL DA REGULATED SUBSTANCES MONITORING Base items 3.000
67000400 CAL MO ENGINEER'S FIELD OFFICE, TYPE A Base items 6.000
67100100 L SUM MOBILIZATION Base items 1.000
70102625 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701606 Base items 1.000
70102632 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701602 Base items 1.000
70102635 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701701 Base items 1.000
70102640 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701801 Base items 1.000
70300100 FOOT SHORT TERM PAVEMENT MARKING Base items 2,665.000
70300150 SQ FT SHORT TERM PAVEMENT MARKING REMOVAL Base items 888.000
70300210 SQ FT TEMPORARY PAVEMENT MARKING LETTERS AND SYMBOLS Base items 339.000
70300220 FOOT TEMPORARY PAVEMENT MARKING - LINE 4" Base items 3,578.000
70300240 FOOT TEMPORARY PAVEMENT MARKING - LINE 6" Base items 1,489.000
70300260 FOOT TEMPORARY PAVEMENT MARKING - LINE 12" Base items 705.000
70300280 FOOT TEMPORARY PAVEMENT MARKING - LINE 24" Base items 1,276.000
70300520 FOOT PAVEMENT MARKING TAPE, TYPE III 4" Base items 1,332.000
78000100 SQ FT THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLS Base items 339.000
78000200 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 4" Base items 3,578.000
78000400 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 6" Base items 1,489.000
78000600 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 12" Base items 705.000
78000650 FOOT THERMOPLASTIC PAVEMENT MARKING - LINE 24" Base items 1,276.000
85000200 EACH MAINTENANCE OF EXISTING TRAFFIC SIGNAL INSTALLATION Base items 1.000
89502376 EACH REBUILD EXISTING HANDHOLE Base items 1.000
X0320050 L SUM CONSTRUCTION LAYOUT (SPECIAL) Base items 1.000
X4240800 SQ FT DETECTABLE WARNINGS (SPECIAL) Base items 160.000
X4400501 FOOT COMBINATION CURB AND GUTTER REMOVAL AND REPLACEMENT LESS THAN OR EQUAL TO 10 FEET Base items 150.000
X6030310 EACH FRAMES AND LIDS TO BE ADJUSTED (SPECIAL) Base items 40.000
Z0001110 EACH GAS VALVE TO BE ADJUSTED Base items 1.000
Z0004562 FOOT COMBINATION CONCRETE CURB AND GUTTER REMOVAL AND REPLACEMENT Base items 50.000
Z0018500 EACH DRAINAGE STRUCTURES TO BE CLEANED Base items 8.000
Z0030850 SQ FT TEMPORARY INFORMATION SIGNING Base items 52.000
Z0033700 FOOT LONGITUDINAL JOINT SEALANT Base items 5,776.000