**QA Environment**
Home > Notice of Letting > Contract Detail

June 12, 2020 Letting 12:00 PM
137-46546

Bulletin Description

Removing damaged raised reflective pavement markers and replacing them with new raised reflective pavement markers within the limits shown.
Region District DBE % VBP % Federal Project #
3 4 0.00 0.00 N/A
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Various
  • VARIOUS
  • D4 REFLECTOR REPL 20-34
  • M-60-032-20
  • 0-01597-4001
Contract Specifics
Completion Date: August 30, 2021
No More Contract Specifics

Ask Subscribe Questions and Answers (1 Submitted / 1 Answered ) Questions not accepted as of June 02, 2020 04:30 PM.

  • is this completion date of August 30 2020 a typo error
    The completion date should be August 30, 2021. This will be corrected in the Transportation Bulletin. (05/11/2020)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
78100100 EACH RAISED REFLECTIVE PAVEMENT MARKER Base items 15,499.000
78300200 EACH RAISED REFLECTIVE PAVEMENT MARKER REMOVAL Base items 15,499.000
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.