January 17, 2020 Letting 10:00 AM
058-74951

Bulletin Description

5.7 miles of patching, cape seal and raised reflective pavement markers on IL 242 from south of Section Line Road in Wayne City to north of I-64.
Region District DBE % VBP % Federal Project #
4 7 3.00 0.00 STPVJJV(485)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Wayne
  • FAP 776
  • (101) PVMT PRSV
  • C-97-028-20
  • 7-51063-0000
Contract Specifics
30 Working Days
No More Contract Specifics

Ask Subscribe Questions and Answers (2 Submitted / 2 Answered ) Questions not accepted as of January 07, 2020 04:30 PM.

  • This project includes Class D patching but there is not a patching schedule included in the plans. Is there a patching schedule available? Is there a mix table available to specify the HMA material? The only Traffic Control pay item is for Standard 701306. Is this the standard meant to cover the patching operations?
    An addendum is forthcoming on this issue. A mix design table will be added to the plans. There is no patching schedule available. Due to the small patching quantity, it is intended for the Contractor to use Standard 701306 for Traffic Control and Protection. It is anticipated that patching will only require 1 or 2 days to complete. (01/06/2020)

  • The drawings call for pavement marking to be removed using the water blasting method. Based on the age of the pavement and the proximity of the edge line to the edge of the pavement water blasting may cause damage to the pavement. Pavement marking removal by grinding will achieve safer results at a cheaper cost. Please review and advise if the pay item can be changed from water blasting to grinding.
    An addendum is forthcoming on this issue. The pay item will be changed to Pavement Marking Removal - Grinding. (01/06/2020)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
40400001 FOOT FIBER-MODIFIED ASPHALT CRACK SEALING Base items 51,781.000
40400020 EACH BUMP REMOVAL Base items 46.000
40500061 SQ YD CAPE SEAL Base items 86,155.000
44201839 SQ YD CLASS D PATCHES, TYPE II, 16 INCH Base items 318.000
44201843 SQ YD CLASS D PATCHES, TYPE III, 16 INCH Base items 18.000
44201845 SQ YD CLASS D PATCHES, TYPE IV, 16 INCH Base items 36.000
67100100 L SUM MOBILIZATION Base items 1.000
70100460 L SUM TRAFFIC CONTROL AND PROTECTION, STANDARD 701306 Base items 1.000
70107025 CAL DA CHANGEABLE MESSAGE SIGN Base items 28.000
70300100 FOOT SHORT TERM PAVEMENT MARKING Base items 15,000.000
70300150 SQ FT SHORT TERM PAVEMENT MARKING REMOVAL Base items 990.000
70300220 FOOT TEMPORARY PAVEMENT MARKING - LINE 4" Base items 72,761.000
78001110 FOOT PAINT PAVEMENT MARKING - LINE 4" Base items 72,761.000
78100100 EACH RAISED REFLECTIVE PAVEMENT MARKER Base items 375.000
78300200 EACH RAISED REFLECTIVE PAVEMENT MARKER REMOVAL Base items 375.000
X0327979 SQ FT PAVEMENT MARKING REMOVAL - GRINDING Base items 23,759.000
No More Pay Items

The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.