20800150
|
CU YD
|
TRENCH BACKFILL
|
Base items
|
114.000
|
|
21400100
|
FOOT
|
GRADING AND SHAPING DITCHES
|
Base items
|
420.000
|
|
25000200
|
ACRE
|
SEEDING, CLASS 2
|
Base items
|
0.250
|
|
25000400
|
POUND
|
NITROGEN FERTILIZER NUTRIENT
|
Base items
|
23.000
|
|
25000500
|
POUND
|
PHOSPHORUS FERTILIZER NUTRIENT
|
Base items
|
23.000
|
|
25000600
|
POUND
|
POTASSIUM FERTILIZER NUTRIENT
|
Base items
|
23.000
|
|
25000700
|
TON
|
AGRICULTURAL GROUND LIMESTONE
|
Base items
|
0.700
|
|
25100115
|
ACRE
|
MULCH, METHOD 2
|
Base items
|
0.250
|
|
28000250
|
POUND
|
TEMPORARY EROSION CONTROL SEEDING
|
Base items
|
25.000
|
|
28000500
|
EACH
|
INLET AND PIPE PROTECTION
|
Base items
|
3.000
|
|
30201700
|
TON
|
PORTLAND CEMENT
|
Base items
|
220.000
|
|
40200800
|
TON
|
AGGREGATE SURFACE COURSE, TYPE B
|
Base items
|
42.000
|
|
40600290
|
POUND
|
BITUMINOUS MATERIALS (TACK COAT)
|
Base items
|
49,894.000
|
|
40600982
|
SQ YD
|
HOT-MIX ASPHALT SURFACE REMOVAL - BUTT JOINT
|
Base items
|
4,198.000
|
|
40600990
|
SQ YD
|
TEMPORARY RAMP
|
Base items
|
1,557.000
|
|
40604050
|
TON
|
HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "C", N50
|
Base items
|
11,681.000
|
|
40733705
|
FOOT
|
LONGITUDINAL JOINT SEALANT
|
Base items
|
35,640.000
|
|
40800050
|
TON
|
INCIDENTAL HOT-MIX ASPHALT SURFACING
|
Base items
|
336.000
|
|
44000155
|
SQ YD
|
HOT-MIX ASPHALT SURFACE REMOVAL, 1 1/2"
|
Base items
|
3,736.000
|
|
44000157
|
SQ YD
|
HOT-MIX ASPHALT SURFACE REMOVAL, 2"
|
Base items
|
2,027.000
|
|
44000165
|
SQ YD
|
HOT-MIX ASPHALT SURFACE REMOVAL, 4"
|
Base items
|
1,056.000
|
|
44000600
|
SQ FT
|
SIDEWALK REMOVAL
|
Base items
|
17.000
|
|
44201789
|
SQ YD
|
CLASS D PATCHES, TYPE II, 12 INCH
|
Base items
|
18.000
|
|
44201794
|
SQ YD
|
CLASS D PATCHES, TYPE III, 12 INCH
|
Base items
|
98.000
|
|
48102100
|
TON
|
AGGREGATE WEDGE SHOULDER, TYPE B
|
Base items
|
1,537.000
|
|
50104400
|
EACH
|
CONCRETE HEADWALL REMOVAL
|
Base items
|
7.000
|
|
50105220
|
FOOT
|
PIPE CULVERT REMOVAL
|
Base items
|
283.000
|
|
54213663
|
EACH
|
PRECAST REINFORCED CONCRETE FLARED END SECTIONS 18"
|
Base items
|
2.000
|
|
54215418
|
EACH
|
CAST-IN-PLACE REINFORCED CONCRETE END SECTIONS 18"
|
Base items
|
2.000
|
|
54215436
|
EACH
|
CAST-IN-PLACE REINFORCED CONCRETE END SECTIONS 36"
|
Base items
|
2.000
|
|
542A0223
|
FOOT
|
PIPE CULVERTS, CLASS A, TYPE 1 18"
|
Base items
|
129.000
|
|
542A0241
|
FOOT
|
PIPE CULVERTS, CLASS A, TYPE 1 36"
|
Base items
|
65.000
|
|
67000400
|
CAL MO
|
ENGINEER'S FIELD OFFICE, TYPE A
|
Base items
|
6.000
|
|
67100100
|
L SUM
|
MOBILIZATION
|
Base items
|
1.000
|
|
70100450
|
L SUM
|
TRAFFIC CONTROL AND PROTECTION, STANDARD 701201
|
Base items
|
1.000
|
|
70100460
|
L SUM
|
TRAFFIC CONTROL AND PROTECTION, STANDARD 701306
|
Base items
|
1.000
|
|
70102620
|
L SUM
|
TRAFFIC CONTROL AND PROTECTION, STANDARD 701501
|
Base items
|
1.000
|
|
70300100
|
FOOT
|
SHORT TERM PAVEMENT MARKING
|
Base items
|
9,720.000
|
|
70300150
|
SQ FT
|
SHORT TERM PAVEMENT MARKING REMOVAL
|
Base items
|
1,079.000
|
|
78001120
|
FOOT
|
PAINT PAVEMENT MARKING - LINE 5"
|
Base items
|
92,809.000
|
|
78100100
|
EACH
|
RAISED REFLECTIVE PAVEMENT MARKER
|
Base items
|
465.000
|
|
78300200
|
EACH
|
RAISED REFLECTIVE PAVEMENT MARKER REMOVAL
|
Base items
|
715.000
|
|
X4200001
|
GALLON
|
CIR-FDR EMULSIFIED ASPHALT
|
Base items
|
139,814.000
|
|
X4200002
|
SQ YD
|
COLD IN-PLACE RECYCLING, 4.0"
|
Base items
|
96,423.000
|
|
X4401198
|
SQ YD
|
HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH
|
Base items
|
96,423.000
|
|
Z0012754
|
SQ FT
|
STRUCTURAL REPAIR OF CONCRETE (DEPTH EQUAL TO OR LESS THAN 5 INCHES)
|
Base items
|
9.000
|
|
Z0034105
|
TON
|
MATERIAL TRANSFER DEVICE
|
Base items
|
11,681.000
|
|
Z0049799
|
EACH
|
PROTECTING OR RESETTING SURVEY MARKERS
|
Base items
|
3.000
|
|
Z0076600
|
HOUR
|
TRAINEES
|
Base items
|
1,500.000
|
$0.80
|
Z0076604
|
HOUR
|
TRAINEES TRAINING PROGRAM GRADUATE
|
Base items
|
1,500.000
|
$15.00
|