The time limit to award this item has been changed from 45 days to 90 days after the scheduled letting.
90 Calendar Days
No More Contract Specifics
AskSubscribe
Questions and Answers (3 Submitted / 3 Answered )
Questions not accepted as of January 11, 2022 04:30 PM.
Plan sheets 3-5 show diff. hatched pvt. areas. However, I do not see any notes or specials regarding the numbering of the phasing/staging, sequence of construction, restrictions to the phasing/staging and closures or work to be completed in each phase before advancement to the next phase/stage is allowed. For example, I see no restrictions of closing both runways and completing all improvements at the same time or combining the areas hatched on plan sheet 4 & 5. Can this information be provided?
The purpose of plan sheets 3-5 is to show the minimum requirements while working in each of the areas. The intent is to maintain at least one open runway at all times and to minimize the closure time of runways and taxiways. The contractor may request combination of the areas, but the decision will be made by the Airport. An addendum will be issued to clarify. (01/19/2022)
Plan sheet #6, note 4 describes lighting adjustment and references a special provision. I see no other information regarding this. Is this work required for this contract?
This work is not required for this contract. An Addendum will be issued. (01/14/2022)
Plan sheet #6 describes work for reflective crack control and the note references a special provision. I see no other information on this. Is this work required for this contract?
This work is not required for this contract. An Addendum will be issued. (01/14/2022)
Authorized Bidders
0593 Brandt Construction Co.
700 4th Street West Milan, IL 61264-2725
Phone: No Record Fax: No Record Email: No Record $775,000.00
2242 Gunther Construction, a div of UCM, Inc.
816 N. Henderson Street Galesburg, IL 61401 PO Box 1488 Galesburg, IL 61402-1488
Phone: No Record Fax: No Record Email: No Record $1,041,572.30
6210 Valley Construction Co.
3610 78th Avenue, West Rock Island, IL 61201
Phone: No Record Fax: No Record Email: No Record
Non Bidders
No requests received
Pay Item #
UOM
Description
Type
Quantity
Unit Price
AR150530
L SUM
TRAFFIC MAINTENANCE
Base items
1.000
AR152480
SQ YD
SHOULDER ADJUSTMENT
Base items
4,556.000
AR401614
TON
BIT. SURF. CSE.-METHOD II, SUPERPAVE
Base items
3,800.000
AR401630
EACH
BITUMINOUS SURFACE TEST SECTION
Base items
1.000
AR401655
SQ YD
BUTT JOINT CONSTRUCTION
Base items
1,351.000
AR401661
FOOT
BITUMINOUS CRACK SEALING
Base items
16,433.000
AR401662
SQ YD
SURFACE COURSE CRACK REPAIR
Base items
1,282.000
AR603510
GALLON
BITUMINOUS TACK COAT
Base items
2,430.000
AR620520
SQ FT
PAVEMENT MARKING-WATERBORNE
Base items
2,938.000
AR620525
SQ FT
PAVEMENT MARKING-BLACK BORDER
Base items
1,247.000
No More Pay Items
The contract details above are for informational purposes only until the Plans and Special Provisions are posted on this web page. If an addendum is posted, the contract details above may be revised. Please continue to check for addenda.