| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 4 | 7 | 0.00 | 0.00 | N/A |
| County(s) | Key Route(s) | Marked Route(s) | Section(s) | State Job #(s) | PPS #(s) |
|---|---|---|---|---|---|
|
|
|
|
|
|
| Contract Specifics |
|---|
| 20 Working Days |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| 60100060 | EACH | CONCRETE HEADWALLS FOR PIPE DRAINS | Base items | 45.000 | |||
| 60100070 | FOOT | SHOULDER REMOVAL AND REPLACEMENT | Base items | 18,486.000 | |||
| 60108200 | FOOT | PIPE UNDERDRAINS 6" (SPECIAL) | Base items | 615.000 | |||
| 60108206 | FOOT | PIPE UNDERDRAINS, TYPE 2, 6" | Base items | 18,196.000 | |||
| 67100100 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| 70100450 | L SUM | TRAFFIC CONTROL AND PROTECTION, STANDARD 701201 | Base items | 1.000 | |||
| 70107025 | CAL DA | CHANGEABLE MESSAGE SIGN | Base items | 84.000 | |||
| No More Pay Items | |||||||