**QA Environment**
Home > Notice of Letting > Contract Detail

June 11, 2021 Letting 12:00 PM
261-89799

Bulletin Description

Remove and replace guardrail at various locations in Fulton County.
Region District DBE % VBP % Federal Project #
3 4 0.00 0.00 G3GR(410)
County(s) Key Route(s) Marked Route(s) Section(s) State Job #(s) PPS #(s)
  • Fulton
  • VARIOUS
  • 20-00900-00-SP
  • C-94-001-21
  • 0-00105-4006
Contract Specifics
55 Working Days
Previously advertised on April 23, 2021 (Item 097).
No More Contract Specifics

Ask Subscribe Questions and Answers (1 Submitted / 1 Answered ) Questions not accepted as of June 01, 2021 04:30 PM.

  • Can the workdays be increased back to 55 Workdays?
    An addendum will be issued. (06/02/2021)

Authorized Bidders

  • No authorized bidders

Non Bidders

  • No requests received
Pay Item # UOM Description Type Quantity Unit Price
20400800 CU YD FURNISHED EXCAVATION Base items 1,020.000
25000300 ACRE SEEDING, CLASS 3 Base items 2.000
25000400 POUND NITROGEN FERTILIZER NUTRIENT Base items 171.000
25000500 POUND PHOSPHORUS FERTILIZER NUTRIENT Base items 171.000
25000600 POUND POTASSIUM FERTILIZER NUTRIENT Base items 171.000
25100115 ACRE MULCH, METHOD 2 Base items 2.000
28000250 POUND TEMPORARY EROSION CONTROL SEEDING Base items 190.000
28000400 FOOT PERIMETER EROSION BARRIER Base items 8,356.000
28100205 TON STONE RIPRAP, CLASS A3 Base items 342.000
48102100 TON AGGREGATE WEDGE SHOULDER, TYPE B Base items 342.000
63000003 FOOT STEEL PLATE BEAM GUARDRAIL, TYPE A, 9 FOOT POSTS Base items 4,243.000
63100075 EACH TRAFFIC BARRIER TERMINAL, TYPE 5A Base items 1.000
63100167 EACH TRAFFIC BARRIER TERMINAL, TYPE 1 (SPECIAL) TANGENT Base items 82.000
63200310 FOOT GUARDRAIL REMOVAL Base items 4,484.000
67100100 L SUM MOBILIZATION Base items 1.000
72501000 EACH TERMINAL MARKER - DIRECT APPLIED Base items 82.000
78200005 EACH GUARDRAIL REFLECTORS, TYPE A Base items 267.000
X6330900 FOOT VERTICAL ADJUSTMENT OF GUARDRAIL Base items 3,157.000
X7010216 L SUM TRAFFIC CONTROL AND PROTECTION, (SPECIAL) Base items 1.000
Z0001002 TON GUARDRAIL AGGREGATE EROSION CONTROL Base items 558.000
Z0013798 L SUM CONSTRUCTION LAYOUT Base items 1.000
No More Pay Items